Total Starts Production at Angolan Oil Project

Total Starts Production at Angolan Oil Project

 

French energy group Total has started production at its Angolan Zinia Phase 2 project, which has estimated resources of 65 million barrels of oil, the company said May 6.

Total added that development of the project was carried out according to schedule and for capital expenditure more than 10% below budget, representing a saving of $150 million.

The project includes the drilling of nine wells and is expected to reach production of 40,000 barrels of oil per day by mid-2022, Total said. It is connected to the existing Pazflor FPSO.

Zinia is located in Block 17 in water depths between 600 m and 1,200 m. Total, which holds a 38% stake, is the block’s operator. Partners are Equinor (22.16%), Exxon Mobil Corp. (19%), BP Exploration Angola Ltd. (15.84%) and Sonangol P&P (5%).

.

Published: 06-05-2021

Share:

[mc4wp_form id=2073]

Global Energy Network - Issue 102

Flip through the latest digital issue of Global Energy Network Magazine.

More News

Latest Magazine Banner

OGV-Energy-Subsea-Magazine-Feb-2026-sq-Banner

WellPro Group Banner

Cegal Banner

Leyton Banner

Advertise with us

Advertise With Us - Global Energy Network