RWE’s Sofia Offshore Wind Farm Reaches 91 Turbines Installed. Only Nine Remaining as North Sea Giant Nears Completion

Wind turbine installation vessel (WTIV) Wind Peak has installed 91 turbines at the Sofia offshore wind farm, under construction approximately 195 kilometres off the UK north-east coast.

The first of the project’s 100 Siemens Gamesa SG 14-222 DD wind turbines was installed in March 2025, and the work reached the halfway mark in September last year.

Cadeler’s Wind Peak, which is carrying components for six turbines per trip from the port of Hull, is supported by IWS’s service operation vessel (SOV) IWS Seawalker.

Vault Aberdeen - https://thevaultaberdeen.com/

Half of the Sofia wind turbines are equipped with recyclable blades, all of which were installed in 2025.

The 1.4 GW Sofia offshore wind farm, owned and developed by RWE, is expected to be commissioned this year, when it will be capable of generating enough electricity to power the equivalent of 1.2 million UK homes, according to its developer.


“Join the companies that smart energy professionals follow – because when you’re featured on GEN, the industry pays attention.”

Tags:
Sofia offshore wind farmWind Peak
Share:

[mc4wp_form id=2073]

Well Management - GEN magazine - Issue 103 - Cover Thumbnail

Flip through the latest digital issue of Global Energy Network Magazine.

More News

Latest Magazine Banner

WellPro Group Banner

Cegal Banner

Leyton Banner

Advertise with us

Advertise With Us - Global Energy Network