Exalo Rig 202 heads to Musuma-1 ahead of November spud

Exalo Rig 202 heads to Musuma-1 ahead of November spud

Invictus Energy began relocating Exalo Rig 202 from the Mukuyu-2 wellsite to the Musuma-1 exploration well location at its Cabora Bassa Project in Zimbabwe, with the well still on track to spud in November.

The move followed completion of the Musuma-1 wellpad, including civil works and access road upgrades, earlier this month. Drilling contractor Exalo Drilling S.A. formally accepted the finished pad before the rig left Mukuyu-2.

The Decommissioning Execution Summit 2027 - https://decomexecutionsummit.com/

After the rig arrives, Exalo will rig up and complete the remaining maintenance and operational readiness work, followed by final rig acceptance before drilling starts. Musuma-1 will test an exploration prospect on the eastern margin of the Cabora Bassa Basin, outside the area of the Mukuyu gas field discovery.


“Your company news doesn’t just get published – it’s seen by the decision makers who matter.”

Tags:
Exalo DrillingExalo Rig 202Invictus EnergyMusuma-1
Share:

[mc4wp_form id=2073]

Drilling Wells and Pipelines - Issue 108 - GEN Magazine Cover

Flip through the latest digital issue of Global Energy Network Magazine.

More News

Latest Magazine Banner

WellPro Group Banner

Cegal Banner

Leyton Banner

Advertise with us

Advertise With Us - Global Energy Network