Serica Energy Says North Eigg Well Costs to Rise GBP3 Mln After Drilling Delayed

Serica Energy Says North Eigg Well Costs to Rise GBP3 Mln After Drilling Delayed

 

Serica Energy PLC said Wednesday that drilling at the North Eigg exploration well has been delayed and that net well cost after tax is expected to rise by around 3 million pounds ($3.4 million).

The U.K. gas producer said operations at the site in the North Sea should take six weeks longer than previously planned to complete and results from the well should now be available in December 2022.

The program was delayed by an equipment failure, it said.

“The technical delays encountered on this project are extremely frustrating but do not impact either the chance of success or the significant prospective volumes of this exploration prospect,” Chief Executive Mitch Flegg said.

Published: 14-09-2022

Share:

[mc4wp_form id=2073]

Well Management - GEN magazine - Issue 103 - Cover Thumbnail

Flip through the latest digital issue of Global Energy Network Magazine.

More News

Latest Magazine Banner

WellPro Group Banner

Cegal Banner

Leyton Banner

Advertise with us

Advertise With Us - Global Energy Network